Building permits and planning permits in Victoria
Two separate approvals from two different people, in a fixed order. Most delays in a Melbourne fitout come from treating them as one thing.
The short answer
New South Wales runs approvals through one consent pathway with a certifier attached. Victoria does not. It runs two independent systems, and the order in which they happen is not negotiable.
Key points
- A planning permit and a building permit are different approvals from different bodies.
- If a planning permit is required, you need it before the building permit can issue.
- The building permit comes from a registered building surveyor, not the council.
- VicSmart decides eligible applications in 10 business days with no public notice.
- At the end you need an occupancy permit or a certificate of final inspection.
New South Wales runs approvals through one consent pathway with a certifier attached. Victoria does not. It runs two independent systems, and the order in which they happen is not negotiable.
The two permits, and who issues them
A planning permit comes from the council, under the Planning and Environment Act 1987 and the planning scheme that applies to your site. It deals with whether the use and the development are acceptable in that location: land use, car parking, amenity, hours, signage, overlays.
A building permit comes from a registered building surveyor, private or municipal, under the Building Act 1993 and the Building Regulations 2018. It deals with whether what you are building complies: structure, fire safety, access, egress, services.
They answer different questions and neither one substitutes for the other. The sequence matters because a building surveyor cannot issue a building permit that would be inconsistent with a planning permit, so if a planning permit is required it has to come first.
Does a medical centre need a planning permit?
It depends on the zone and the schedule to that zone, which is why the honest answer to this question always starts with the address.
In many commercial zones a medical centre is a permit-required use rather than an as-of-right one, and changing an office or a shop into a clinic is a change of use that needs assessment even where no building work is visible from the street. Car parking is usually the deciding issue: the planning scheme sets a rate for the use, and an existing tenancy that satisfied it as a shop may not satisfy it as a practice with six consulting rooms.
Overlays complicate it further. Heritage, design and development, and parking overlays each add their own triggers, and a site can sit under more than one.
This is a question for a town planner reading the scheme against your specific address, and it is worth paying for before you sign rather than after. It is the single most common reason a Melbourne tenancy that looked ideal turns out not to be.
VicSmart, and when it helps
VicSmart is a streamlined planning permit pathway. Where an application qualifies, the council decides it within 10 business days rather than the standard 60 day statutory period, and the application is exempt from public notice and from third party review.
The catch is eligibility. An application only qualifies if it is listed as a VicSmart class in the relevant planning scheme and meets the criteria for that class, in the specified zone or overlay. It is not a fast lane you can request; it is a category your application either falls into or does not.
The other condition is completeness. The 10 day clock assumes the council has everything it needs at lodgement, so a VicSmart application submitted with gaps loses the advantage it was lodged for.
What the building surveyor needs
Once planning is resolved, the building permit is a documentation exercise, and it moves at the speed of your consultants rather than the council.
- Architectural drawings and specifications
- Structural documentation where you are touching the structure
- Mechanical, hydraulic and electrical design, which for a clinical tenancy carries AS 1668.2 ventilation rates an office fitout does not
- An access report against AS 1428.1
- Fire safety documentation, and a performance solution where anything departs from the deemed-to-satisfy provisions
- Any report and consent from council required under the regulations
The classification question sits underneath all of it. A tenancy that becomes Class 9a carries construction requirements a Class 5 or Class 6 tenancy does not, and which class you land in is a determination the building surveyor makes rather than a label you choose.
What you need at the end
The building permit itself specifies which completion document applies. For a fitout that changes the use or the classification it is normally an occupancy permit, issued by the building surveyor once they are satisfied the building is suitable to occupy. For some alteration work it is a certificate of final inspection instead, which closes off the permit without certifying suitability for occupation.
You cannot lawfully open on the strength of a finished fitout. The rest of the detail, and what usually holds these up, is in the guide to occupancy certificates.
Victoria also carries an ongoing obligation that surprises tenants from other states. Essential safety measures identified on the permit have to be maintained for the life of the building, and the building owner is required to prepare an annual essential safety measures report. It is small money and easy to do, and it is the sort of thing that surfaces during a lease assignment when nobody has done it for four years.
A note on who regulates this now
Victoria's building regulator changed. The Victorian Building Authority was abolished and its functions moved to the Building and Plumbing Commission on 1 July 2025, which now handles registration of building surveyors, enforcement and dispute resolution in one body. If you are reading older guidance that refers to the VBA, the substance is usually still right but the regulator's name is not.
Sources and further reading
Planning Victoria on planning schemes and VicSmart, and the Building and Plumbing Commission on building permits and registered building surveyors. Whether a permit is required on a specific site is a question for a town planner and a building surveyor reading it against that address.
Victorian planning schemes, permit pathways and the VicSmart streamlined assessment process.
Victoria's building regulator since 1 July 2025, when it replaced the Victorian Building Authority. Building permits, registered building surveyors and occupancy permits.
The National Construction Code: building classification, fire separation, egress, sanitary provisions and access.
Source for AS/NZS 4815 and 4187 reprocessing, AS 1428.1 access and AS 1668.2 ventilation. The standards themselves are purchased, not free.
Questions
Do I need a planning permit or a building permit in Victoria?
Potentially both, and they are different approvals from different bodies. The planning permit comes from the council and deals with whether the use is acceptable at that location. The building permit comes from a registered building surveyor and deals with whether the work complies. Where a planning permit is required it must be obtained first, because a building surveyor cannot issue a permit inconsistent with it.
Who issues a building permit in Victoria?
A registered building surveyor, either private or municipal, under the Building Act 1993 and the Building Regulations 2018. Not the council, which is the point most often misunderstood by tenants coming from New South Wales. The surveyor also carries out the mandatory inspections and issues the occupancy permit or certificate of final inspection at the end.
Does converting a shop to a medical centre need a planning permit in Victoria?
Usually, because it is a change of use, and in many commercial zones a medical centre is a permit-required use. Car parking is commonly the deciding issue, since the planning scheme sets a rate for the use and a tenancy that satisfied it as a shop may not as a practice. It depends on the zone, the schedule and any overlays, so it is a question for a town planner reading the scheme against your address.
What is VicSmart?
A streamlined planning permit pathway where the council decides the application in 10 business days instead of the standard 60 day period, with no public notice and no third party review. It only applies to applications that are listed as a VicSmart class in the relevant planning scheme and meet that class's criteria, and the clock assumes a complete application at lodgement.
How long does a building permit take in Victoria?
The permit itself is usually a matter of weeks once documentation is complete, because it moves at the speed of your consultants rather than a council queue. The variable is the planning permit in front of it: 10 business days under VicSmart, or 60 statutory days plus advertising and any objections on a standard application.
What is an essential safety measures report?
A Victorian requirement. Safety measures identified on the building permit must be maintained for the life of the building, and the owner has to prepare an annual report confirming it. It is inexpensive and routinely forgotten, and it surfaces during a lease assignment when nobody has done it for years.
Related
Occupancy certificates
The document that lets you legally open, state by state.
Read onHow long a fitout takes
Why approvals rather than build time set your opening date.
Read onMedical fitouts in Melbourne
What we check on a Victorian tenancy.
Read onMedical centre design
The patient path, then the rooms along it.
Read onSend us the floor plan
A site assessment tells you what the tenancy can take and what it will cost to get there, ideally before you have signed for it.